Lovochemie Nitric Acid Plant, Lovosice, Czech Republic

Email-Icon
 
Print-Icon
 
Link-to-us
key facts
Key Data
Plant owner
Lovochemie AS
Project completion
September 2003
Project inauguration
April 2002
Production capacity
300,000t/yr
Project cost
Koruna 1.3bn
Lumpsum turnkey contract
Technip
Construction contract
Chemoprojekt

During 2000 Lovochemie, a Czech Republic-based fertiliser producer, decided to invest Koruna 1.3bn ($45m) to build a new nitric acid production plant.

The unit, which is called KD 6, has a capacity of 900t/d (300,000t/yr) of 100% nitric acid. The production plant replaced four old plants, KD 1-4, which have been in operation for almost 50 years.

"The unit has a capacity of 900t/d (300,000t/yr) of 100% nitric acid."

The new production facility is located at the Lovosice fertiliser complex (Lovochemie AS) in North Bohemia, Lovosice, Czech Republic, and was officially inaugurated in April 2003.

Final guarantee testing and plant hand over to the customer was completed at the end of May 2003. The production unit employs 15 people.

Lovochemie is the Czech Republic's largest producer of fertilisers. Most of the nitric acid will be used to make a number of nitrogenous and compound fertilisers.

LUMPSUM TURNKEY CONTRACT

In April 2001 Technip, now known as Technip-Coflexip, announced that it had been awarded a lumpsum turnkey contract by Lovochemie for the construction of the nitric acid plant. Under the terms of the contract, which was valued at €27m, Technip was responsible for the basic and detailed engineering, supply of equipment and construction.

The project was executed by the Technip group's local engineering affiliate Chemoprojekt Praha. The company is a Prague-based design, engineering and contracting organisation.

CONSTRUCTION

Construction work began in the first half of 2001 and the project was completed in September 2002. Commissioning and official start-up had been planned for November of the same year. The official start-up was eventually postponed until April 2003 due to major flooding across the Czech Republic during August 2002 (five months behind the original schedule).

NITRIC ACID STORAGE FACILITY

Chemoprojekt was also responsible for building a 6,000m³ nitric acid bulk storage facility for the production plant. The contract included project documentation, procurement, installation and site management.

SINGLE PRESSURE PROCESS TECHNOLOGY

The nitric acid plant uses single pressure process technology provided by France's Grande Paroisse. In a single pressure plant the oxidation and absorption take place at the same pressure. The process is said to benefit from proven reliability, low investment costs and low NOx tail gas content.

CHEMPROJEKT'S RENOX PROCESS

Chemoprojekt has provided its selective catalytic reduction, (Renox) process for the nitric acid plant. This process is used to decrease the NOx content in the outlet gases. Chemoprojekt says this technology offers the advantage of, amongst other things, low investment costs, high catalyst conversion and high heat recovery.

FINANCING

The Koruna 1.3bn investment in the plant comprised Koruna 500m financed by credit from Komerc ni Banka and Koruna 300m as a loan from an unnamed foreign customer. The rest was provided from Lovochemie's own resources.

ENVIRONMENTAL IMPACT

An environmental impact assessment was carried out in relation to the construction of the nitric acid plant KD 6. After a public discussion, the Ministry of Environment declared that it was in favour of the construction of the production plant.

The plant also delivers steam which Lovochemie says provides significant savings in terms of fuel. At the same time the consumption of ammonia per unit of produced nitric acid as well as emissions of nitrogen oxide is reduced. The facility complies with tough EC emission limits.

ENVIRONMENTAL MITIGATION

The Nitrous Oxide Emission Reduction Project at Lovochemie instigated in 2004–2005 comprised the installation of a new catalyst technology for the reduction of N2O emissions from nitric acid production.

"The new catalyst and associated monitoring equipment is hoped to lead to the reduction of a major part of erroneous N2O emissions."

The new catalyst and associated monitoring equipment is hoped to lead to the reduction of a major part of erroneous N2O emissions from the production process. Lovochemie AS chose Hereaus of Germany as the supplier of the new catalyst technology and also contracted them to install and monitor the process.

The NOX reduction project was supported by Lovochemie AS, the Danish Environmental Protection Agency (DEPA), the Czech Ministry of Environment, and the Danish project developer Grue & Hornstrup A/S and technical consultant Korsbæk & Partners KS.

The development of the project and its implementation were completed by the end of 2005 (250,000t CO2 equivalent).



Expand Image Expand Image
Plans to develop the nitric acid plant were put in place during 2000. The proposed 900t/d nitric acid plant would replace old production capacity.



Expand Image Expand Image
Chemoprojekt was responsible for the construction of the production plant as well as the nitric acid storage facilities. Construction was started during the first half of 2001.



Expand Image Expand Image
Construction of the nitric plant was completed in 2002. During the first half of 2003 the nitric acid plant became fully operational. Lovochemie will use most of the nitric acid to make a number of nitrogenous fertilisers.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the chemicals industry